Thursday, Aug 15, 2024 @ 10:30 am

Public Service Commission of Wisconsin 
Hill Farms State Office Building* 
Hearing Room S105, 1st Floor** 
4822 Madison Yards Way 
Madison, Wisconsin 

*This building is physically accessible for individuals with disabilities. 

**Those attending the open meeting in person will need to check-in at the security desk at the  employee entrance directly across from the parking structure. As the location is in a publicly  accessible space on the first floor, you may then go directly to the PSC Hearing Room without  obtaining a visitor access badge. 

NEW 

This in-person meeting is being broadcast live and is available for replay on the Commission’s  YouTube channel. You can also access our YouTube channel via the “Live Broadcast” button  on the Commission’s website (http://psc.wi.gov/) 

If you need reasonable accommodation due to a disability, or other accommodation to access this  meeting, please contact the Commission at (608) 266-1265. 

Open Meeting Agenda for Thursday, August 15, 2024, at 10:30 a.m.

1. Minutes of the open meeting of Thursday, August 1, 2024 

2. 1125-RW-180 – Tolls to be Charged for the Chippewa and Flambeau Improvement Company  for the Six Months Period Ending June 30, 2024 (proposed notice of investigation) 

3. 1880-CE-107 – Application of City of Evansville, as an Electric Public Utility, for Authority  to Purchase and Install a New Replacement Transformer and Construct Other Associated  Facilities at the Union Townline Substation, in the City of Evansville, Rock County,  Wisconsin (proposed notice of investigation) 

4. 1880-CE-108 – Application of City of Evansville, as an Electric Public Utility, for Authority  to Construct a Distribution Equipment Installation for a 13 MVA Load from an Industrial  Development, in the City of Evansville, Rock County, Wisconsin (proposed notice of  investigation)

5. 4220-GP-2024 – Northern States Power Company – Wisconsin’s Gas Supply Plan for the  Period Beginning November 1, 2024 (proposed notice of investigation) 

6. 5370-LS-101 – Application of the City of Sheboygan, as a Public Water Utility, for Authority  to Implement a Financial Assistance Program for Customer-Side Lead Service Line  Replacement, in the City of Sheboygan, Sheboygan County, Wisconsin (proposed notice of  investigation) 

7. 6630-GP-2024 – Wisconsin Electric Power Company Gas Supply Plan for the Period  Beginning November 1, 2024 (proposed notice of investigation) 

8. 6650-GP-2024 – Wisconsin Gas LLC Gas Supply Plan for the Period Beginning November 1,  2024 (proposed notice of investigation) 

9. 6680-GP-2024 – Wisconsin Power and Light Company Gas Supply Plan for the Period  Beginning November 1, 2024 (proposed notice of investigation) 

10. 6680-TG-125 – Application of Wisconsin Power and Light Company for Approval of  Revisions to the Gas Cost Recovery Mechanism and Refund Provision Tariff Sheet No.  21.011, 21.02, and 23.62 (proposed notice of investigation) 

11. 6725-RW-180 – Tolls to be Charged for the Wisconsin Valley Improvement Company for the  Six Months Period Ending June 30, 2024 (proposed notice of investigation) 

12. 2360-WR-106 – Application of the Village of Greendale, Milwaukee County, Wisconsin, as a  Water Public Utility, for Authority to Adjust Water Rates (proposed notice of proceeding) 

13. 2460-WR-103 – Application of the Harmony Grove Sanitary District No. 1, Columbia  County, Wisconsin, as a Water Public Utility, for Authority to Adjust Water Rates (proposed  notice of proceeding)

14. 2580-WR-103 – Application of the Village of Hollandale, Iowa County, Wisconsin, as a  Water Public Utility, for Authority to Adjust Water Rates (proposed notice of proceeding) 

15. 2655-WR-101 – Application of the Village of Hustler, Juneau County, Wisconsin, as a Water  Public Utility, for Authority to Adjust Water Rates (proposed notice of proceeding) 

16. 3060-WR-101 – Application of the Laona Sanitary District No. 1, Forest County, Wisconsin,  as a Water Public Utility, for Authority to Adjust Water Rates (proposed notice of  proceeding) 

17. 3420-WR-107 – Application of the City of Marshfield, Wood and Marathon Counties,  Wisconsin, as a Water Public Utility, for Authority to Adjust Water Rates (proposed notice  of proceeding) 

18. 4670-WR-104 – Application of the City of Pittsville, Wood County, Wisconsin, as a Water  Public Utility, for Authority to Adjust Water Rates (proposed notice of proceeding) 

19. 5960-WR-103 – Application of the Troy Center Sanitary District No. 1, Walworth County,  Wisconsin, as a Water Public Utility, for Authority to Adjust Water Rates (proposed notice  of proceeding) 

20. 6360-WR-111 – Application of the City of West Allis, Milwaukee County, Wisconsin, as a  Water Public Utility, for Authority to Adjust Water Rates (proposed notice of proceeding) 

21. 6630-CE-316 – Application of Wisconsin Electric Power Company for a Certificate of Public  Convenience and Necessity to Construct and Operate the Paris Reciprocating Internal  Combustion Engines Project, Consisting of Seven Natural Gas-Fired Reciprocating Internal  Combustion Engines Generating up to 128 MW Total at the Lakeshore Capacity  Improvement Project Regulator Station in the Town of Paris, Kenosha County, Wisconsin  (proposed notice of proceeding) 

22. 6630-CE-317 – Application of Wisconsin Electric Power Company for a Certificate of Public  Convenience and Necessity to Construct and Operate the South Oak Creek Combustion  Turbine Project, Consisting of Five Natural Gas-Fired Single-Cycle Combustion Turbines 

Generating up to 1100 MW total at the South Oak Creek Facility in the City of Oak Creek,  Milwaukee County, Wisconsin (proposed notice of proceeding) 

23. 9300-PLI-126 – Investigation of the Complaint of Enbridge Energy, Limited Partnership  against CF Construction, LLC, Referred to the Commission Pursuant to Wis. Stat. §  182.0175(3)(br)2. (draft final decision) 

24. 4220-TE-117 – Application of Northern States Power Company, for Approval of Voluntary  Renewable Energy Rider Customer Service Agreements Tariff for the Lake Hallie Solar  Electricity Generating Facility (suggested minute) (KC/TNB/BC/TM/SJ memorandum of  7/9/24) 

25. 6680-AF-107 – Request of Wisconsin Power and Light Company for Deferral of  Construction Cost Overruns Associated with Solar Generation Projects Authorized in Docket  6680-CE-182 and 6680-CE-183 

Request to Reopen Final Decision (suggested minute) (CES memorandum of 8/6/24) 

* * * 

The next open meeting is scheduled for Thursday, August 22, 2024, at 10:30 a.m.